The Udon Green Initiatives are structured around a phased, execution-driven milestone framework designed to de-risk development, demonstrate early traction, and enable timely scale-up of biomass, composting, and renewable-power assets.
Milestones are aligned with regulatory processes, community engagement, and investment readiness, ensuring transparency and accountability for institutional investors.
Policy & Institutional Engagement
Initial engagement completed with the Provincial Agricultural Office of Udon Thani
Formal consultations held with the Udon Thani Provincial Farmers Council
Strong institutional interest confirmed for an integrated biomass supply-chain approach aligned with the Clean Air Act and climate legislation
Project Structuring
Conceptual design completed for a province-wide biomass aggregation model covering 1,867 villages
Preliminary clustering defined for 153 Tambon-level biomass warehouses
Initial framework designed for four (4) district-cluster compost plants and four (4) biomass power plants, co-located for logistics efficiency
Feedstock & Supply Chain
Preliminary feedstock mapping completed for rice straw and sugarcane leaves
Draft community participation model defined through village and Tambon-level enterprises
Initial logistics flow validated (village → Tambon warehouse → compost / power plant)
Community & Land Readiness
Formal MOUs targeted with Tambon-level community enterprises
Identification and preliminary securing of land for:
Biomass warehouses
Compost plants
Biomass power plant clusters
Pilot Infrastructure Deployment
Pilot village-scale biomass warehouses commissioned
Pilot compost production initiated to generate early farmer income
Digital MRV baseline established for biomass collection and handling
Investment & Structuring
SPV structure finalized for Udon platform
Equity structure confirmed
Community 10-20%
REpow + Strategic Partners 10-20%
VC 30-40%
DFI 30-40%
Initial investor discussions advanced with Climate VCs and DFIs
Scale-Up of Circular Infrastructure
Full rollout of Tambon-scale biomass warehouses
Commissioning of district-cluster compost plants
Transition from pilot to commercial compost operations
Power Project Development
Submission of biomass power plant license applications
PPA discussions initiated (EGAT / PEA and/or direct PPA structures)
EPC pre-selection and cost finalization
Digital MRV & ESG
Full deployment of Digital MRV across villages, warehouses, and compost plants
Independent ESG and clean-air impact reporting initiated
Carbon-credit eligibility assessment completed
Biomass Power Plant Commissioning
Construction and COD of four (4) biomass power plants
Long-term feedstock contracts activated
Compost plants transition feedstock from straw/leaves to cassava rhizomes and other residues
Platform Optimization
Stable baseload renewable electricity generation
Portfolio-level operational optimization
Preparation for refinancing, YieldCo aggregation, or strategic exit
All milestones tracked through Digital MRV and project dashboards
Quarterly progress reporting to investors
Independent verification of feedstock, environmental impact, and social outcomes
The Udon Green Initiatives are not a concept-stage project, but a structured, milestone-driven platform progressing from community-based biomass aggregation to industrial-scale renewable-energy infrastructure.
Each milestone is designed to unlock the next layer of value, reduce development risk, and demonstrate execution capability—providing DFIs and Climate VCs with clear visibility on timing, capital deployment, and impact delivery.